| 20 Aug 2008 |
 |
| | | | | | | | |

| 14 Dec 2003 |
|
|
|
 |
| Electrical first fix finished. Almost all the first floor partitioning finished. Shuttering in place for the roof of the boiler room and orangery. Inside/Outside bath/shower nearly ready for glazing. Final revised plans for the master bedroom. |
| |
|
|
|
| 05 Dec 2003 |
|
|
|
 |
| The inside/outside shower/bath structure is in place - just need to wait for the cement ring support to go off. |
| |
|
|
|
| 05 Oct 2003 |
|
|
|
 |
| Back to work. The first floor is pretty much plaster-boarded out now and Ed and I are starting work on wiring. |
| |
|
|
|
| 01 Aug 2003 |
|
|
|
 |
| Well, I am camping in the house as there are guests in the farmhouse - It's very comfortable, despite my not having a working shower as yet. Hell, just means swimming in the morning and washing hair in the upstairs sink. Got a little temporary kitchen going downstairs, it's all working fine. |
| |
|
|
|
| 01 Jul 2003 |
|
|
|
 |
| Well, kicking back for the summer now - The temperatures are regularly in the high 30s and it is too damn hot to work... + there are simply too many parties to go to!!! |
| |
|
|
|
|


From: Ravi
Date: 31 Jan 2006