21 Nov 2008


14 Dec 2003      
Electrical first fix finished. Almost all the first floor partitioning finished. Shuttering in place for the roof of the boiler room and orangery. Inside/Outside bath/shower nearly ready for glazing. Final revised plans for the master bedroom.
       

05 Dec 2003      
The inside/outside shower/bath structure is in place - just need to wait for the cement ring support to go off.
       

05 Oct 2003      
Back to work. The first floor is pretty much plaster-boarded out now and Ed and I are starting work on wiring.
       

01 Aug 2003      
Well, I am camping in the house as there are guests in the farmhouse - It's very comfortable, despite my not having a working shower as yet. Hell, just means swimming in the morning and washing hair in the upstairs sink. Got a little temporary kitchen going downstairs, it's all working fine.
       

01 Jul 2003      
Well, kicking back for the summer now - The temperatures are regularly in the high 30s and it is too damn hot to work... + there are simply too many parties to go to!!!
       





From: Ravi
Date: 31 Jan 2006
The guestbook has been temporarily suspended as we were getting WAY too much spam!!



All material on this site is © 2002 Matthew Weinreb, with the exception of the logos and materials of my partner companies.
Site developed by Ravi Ramamrutham © 2002